﻿_id	map_id	size_kv	status	eia_date	eia_status	descrip	circuit	cross_section(mm2)	dist_line	year	grant_inv	reference	last_update	language
1	1	230	Existing lines	""	""	Vietnam Border- Takeo Substation	2	400	50	2009	ADB-NDF	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
2	2	115	Existing lines	""	""	Kirirom I-KiriromIII	1	150	32	2012	BOT	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
3	3	230	Existing lines	""	""	 Kampot Substation - TakeoSubstation	2	450	73	2011	KfW	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
4	4	230	Existing lines	""	""	Kampot Substation-Kamchay Hydropower Plant	2	400	11	2012	BOT	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
5	5	230	Existing lines	Jan-09	Feasibility study	Phnom Penh- Kampong Chhnang-Pursat- Battambong	2	630	297	2012	BOT	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
6	6	230	Existing lines	""	""	Pursat Substation- Osom Substation	2	630	132	2012	BOT	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
7	7	230	Existing lines	""	""	Kampot Substation -Stung Hav Substation	2	630	81.62	2013	ADB-JICA	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
8	8	230	Existing lines	""	""	GS6-  Kampong Chhnang  Substation	2	2x400	97.18	2013	BOT	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
9	9	230	Existing lines	""	""	 Osom Substation-Lower Reussey Chrum Hydropower Plant	2	2x400	42	2013	BOT	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
10	10	230	Existing lines	""	""	Phnom Penh Loop line(WPP-SPP)	2	2x630	48	2014	China Exim Bank	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
11	11	230	Existing lines	""	""	Lower Upper Reussey Chrum Hydropower-Tatay Hydropower	2	2x400	38	2014	BOT	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
12	12	115	Existing lines	""	""	Banteay Meanchey Substation-Battambang Substation	1	400	53	2007	BOT	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
13	13	115	Existing lines	""	""	GS4-GS1	1	2x250	29.8	2009	WB	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
14	15	230	Existing lines	""	""	Atay Hydropower Plan- Osom Substation	2	630	17.8	2013	BOT	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
15	16	115	Existing lines	""	""	Stung Hav Substation- Shihanouk Ville Substation	2	400	11	2014	JICA	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
16	17	115	Existing lines	""	""	 Chhuk Substation- Banteay Meas Substation	1	400	12	2014	EDC	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
17	18	115	Existing lines	""	""	GS3-GS2	1	2x250	11.85	1999	""	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
18	19	115	Existing lines	""	""	Kampong Speu Substation-Kirirom I	1	150	65.04	2002	""	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
19	20	115	Existing lines	""	""	GS1- Kampong Speu Substation	1	150	40.93	2002	""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
20	21	115	Existing lines	""	""	Thai Border-Substation IE	2	400	4	2007	""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
21	22	115	Existing lines	""	""	Substation IE-Substation Banteay Meanchey	2	400	43	2007	""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
22	23	115	Existing lines	""	""	Substation Banteay Meanchey-Substation Siemreap	1	400	85	2007	""	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
23	24	230	Under construction	""	""	Kratie-Stung Treng		""	126	2012	INDIA	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
24	25	230	Under construction	""	""	Phnom Penh-Sihanoukville, along national road 4		""	220	2013	CHMC	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
25	26	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
26	27	115	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
27	28	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
28	51	115	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
29	29	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
30	31	115	Under construction	""	""	East Phnom Penh- Neakleung-Svay Rieng		""	120	2014	CHMC	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
31	32	115	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
32	33	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
33	34	115	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
34	35	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
35	36	230	Under construction	""	""	Kampong Cham-Kratie		""	110	2012	CUPL	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
36	37	230	Under study	""	""	Lao PDR (Ban Sok)-Stung Treng-Vietnam (Tay Ninh)		""	220	2019	ADB	EDC_Anual_Report_2014__00.00.2014.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
37	38	115	Under construction	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf;Report_on_Power_Sector_2010_Edition.pdf;Progress_of_Cambodia_Power_Development__26.11.2009.pdf;Hydropower_Development_in_Cambodia__01.12.2011.pdf	2016-07-15T00:00:00	English
38	40	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf	2016-07-15T00:00:00	English
39	41	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf;Cambodia_energy_status_ development__16.03.2011.pdf	2016-07-15T00:00:00	English
40	42	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English
41	43	115	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English
42	44	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English
43	45	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English
44	46	230	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English
45	47	115	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English
46	48	115	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English
47	49	115	Under study	""	""	""		""			""	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English
48	50	230	Under study	""	""	Stung Treng-Lao PDR (construct substation in Stung Treng)		""	56	2012	WB	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English
49	39	230	Existing lines	""	""	Takeo Substation-GS4	2	630	47	2009	ADB-NDF	EDC_Anual_Report_2014__00.00.2014.pdf	2016-07-15T00:00:00	English