[Draft] Environmental and social impact assessment (ESIA) on Kamchay Hydroelectric Project in Kampot Province of SINOHYDRO KAMCHAY HYDROELECTRIC CO., LTD.
Published by: Open Development Cambodia
Data Resources (19)
Data Resource Preview - Table of contents
Thông tin khác
Miền | Giá trị |
---|---|
Vùng địa lý (phạm vi không gian) |
|
Chủ đề |
|
Loại tài liệu | Environmental Impact Assessment |
Các bên ký kết |
|
Đối tượng thuộc chính phủ (nhiều) |
|
Giấy phép | Creative Commons Attribution Share-Alike |
Bản quyền | No |
Hạn chế truy cập và sử dụng |
By accessing this website or database, users agree to take full responsibility for reliance on any site information provided and to hold harmless and waive any and all liability against individuals or entities associated with its development, form and content for any loss, harm or damage suffered as a result of its use. |
Phiên bản/ Ấn phẩm | 1 |
Ngôn ngữ của tài liệu |
|
(Các) Tỉnh |
|
Thông tin tham khảo Metadata. |
Metadata last updated on 2021-04-22. For inquiries contact: Open Development Cambodia, Email: contact@opendevcam.net, Website: http://www.opendevcam.net Address: 43 St. 208, Phnom Penh, Cambodia. |
Ngày ký | 23 tháng 2, 2006 |
Liên hệ |
SAWAC Consultants for Development Address: No. 01, Street 259, Sangkat Teuk L'ak1, Khan Tuol Kork, Phnom Penh. |
Party's obligation in the implementation of the project |
Sinohydro KAMCHAY Hydroelectric Project Co., Ltd is a 44-year hydropower investment company in Cambodia with a four-year construction period. The company is a subsidiary of SINOHYDRO Corporation Limited (SINOHYDRO) of the People's Republic of China, which bid openly and internationally for investment rights from June 2004 to January 2005. The Company was ranked No. 1 and on February 23, 2006, the Ministry of Industry, Mines and Energy and the Ministry of Economy and Finance signed a "BOT" investment agreement for the Kamchay Hydropower Development Project in Kampot Province with the total investment value of 330 million US dollars. |
Job creation summary |
|
Số lượng công việc được tạo | 40.0 |
Training summary |
This project will train Cambodian professional officers to continue the process after the company terminates its contract with the Royal Government. |
Environmental protection obligation |
The Company has implemented mitigation measures during the design and construction phase of the project, the implementation phase and the final stage of the project, including the study of topography, erosion, surface water, hydrology, air quality, water quality, soil quality, biological resources, forest resources and wildlife sanctuaries, livelihoods and occupations of local communities, traditions, culture and religion, water supply systems, roads, transportation, public health, aesthetics and risks. |
Socio-cultural protection |
The project will reduce the use of electricity from gasoline and coal-fired power plants, which emit carbon monoxide and carbon dioxide or carbon dioxide as a source of greenhouse gases. The 230 KV high voltage transmission line from the transformer of the first, second and third power plants of Kamchay Hydropower Plant with a length of 11.05 km to Kampot substation will have additional power supply to Sihanoukville, Takeo and Phnom Penh to meet the needs of effective development for the country. In line with the poverty reduction policy of the Royal Government of Cambodia, this project will make people have access to cheap electricity in agriculture. In addition, people can have a better life when they have this energy for handicrafts and also attract large and small factories in the area. On the other hand, the project has direct payments to the national budget revenue through the payment of taxes. |
Environmental fund summary |
|
Dự án liên quan |
https://opendevelopmentcambodia.net/news/cambodia-dams-benefits-exclude-people-in-its-vicinity/#!/story=post-77940 |
Tài liệu tham khảo kế thừa | Draft_ESIA_Sinohydro_Kamchay_Hydroelectric__00.04.2011.pdf |
Các từ khóa | Hydroelectric,Kamchay,China,hydro power,dam |
Định danh hợp đồng mở | ocds-miumsd-e24128c7-a0ab-466a-9d8d-83ed948e8a8f |
Ngày đăng tải | tháng 7 20, 2021, 09:02 (UTC) |
Ngày chỉnh sửa, cập nhật | tháng 10 5, 2022, 08:40 (UTC) |